CENECO SETS POWER INTERRUPTIONS ON DECEMBER 5, 6 AND 7
Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on December 5 (Saturday), 6 (Sunday), and 7 (Monday). This is to ensure reliability of distribution lines to avoid further serious damages that will result to major interruptions. Details of these outages are as follows:
Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on December 5 (Saturday), 6 (Sunday), and 7 (Monday). This is to ensure reliability of distribution lines to avoid further serious damages that will result to major interruptions. Details of these outages are as follows:
Date: December 5, 2020 – Saturday
Reasons:
• Preventive maintenance and servicing of 30MVA power transformer and correction of hotspot
Time: 7am to 8am and 3pm to 4pm
Areas Affected: MUF1 Prk. Manayaosayao, Canlaon View Subd., Tanduay, Proper Blumintritt
MUF2 Marian missionaries, Hda. Josefa II, Hda. Olive 2, Had.Jovelanos, Binitin, Candongon, Cansilayan, Murcia and Don Salvador Benedicto, the whole municipalities of Murcia and Don Salvador Benedicto, Brgy. Lopez Jaena to Mambucal, Had. Mala, Co Salazar, (R14): Brgy. Alegria, Brgy. Sta. Cruz, CPAC (Central Philippine Adventist College), Country Homes, Firmville, Iglau-an, Talotog, Buenavista, Salvacion, Caliban
Date: December 6, 2020 – Sunday
Reasons:
• Relocation of two 35ft. 3-phase primary concrete poles to lot boundary with one 25kVa distribution transformer and accessories
Time: 9am to 3pm
Areas Affected: BF4 (portion only) Country Homes Phase 3, Brgy. Estefania, Bacolod City
Date: December 7, 2020 – Monday
Reasons:
• Replacement of three 30ft. rotten open secondary wood poles with three 30ft. steel poles and transfer of secondary assemblies to newly-erected steel poles; and
• Replacement and relocation of one 30ft. open secondary wood pole to lot boundary for safety.
Time: 9am to 3pm
Areas Affected: MF4 (portion only)
Prk. Tunay and Prk. Kamunsil, Brgy. Bata
Time: 9am to 12nn
Areas Affected: MF4 (portion only) Natividad Street and surrounding areas, Phase 2 Gold Crest Subd., Brgy. Bata, Bacolod City
Electricity consumers are further advised that, in the event of any power interruption, electrical switch/es should be turned-off for safety reasons.
When electricity supply resumes, please provide allowance of about 10-15 minutes before switching on all electrical appliances and facilities to avoid power surge.
For inquiries, please call your CENECO Call Center at telephone numbers 458-6777 local 1101, 1102, 1103 and 1107.
Sorry for the inconvenience.
(SGD.) MARIA AGNES L. CLARO
OIC – Office of the General Manager