Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on January 29, Friday. This is to ensure stability of distribution lines to avoid further serious damages that will result to major interruptions. Details of this outage are as follows:
Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on January 29, Friday. This is to ensure stability of distribution lines to avoid further serious damages that will result to major interruptions. Details of this outage are as follows:
Date: January 29, 2021 – Friday
Reasons:
• Mid-span erection of one 40ft. concrete pole with C14 3-phase primary construction assembly and installation of one 50kVa private distribution transformer with its accessories; and
• Tree clearing activities along the line.
Time: 6am to 8am
Areas Affected: AF1 Portion of Alijis Road (Alijis Substation to areas before Good Year), Bacolod Girl’s Home, Prk. Pag-asa, John B. Lacson College, Pauline Village, ECC Villas, Greenplains Subd., Akina Village, South Residences, Araneta Highway (Monark Eqpt. down to Medalla Elem. School), Bel-Air Subd., Woodstock Subd., Villa Cristina Subd., Prk. 8 Baybay, Gardenville Subd., Florenceville, ManVille Subd., Akina Village
Electricity consumers are further advised that, in the event of any power interruption, electrical switch/es should be turned-off for safety reasons.
When electricity supply resumes, please provide allowance of about 10-15 minutes before switching on all electrical appliances and facilities to avoid power surge. For inquiries, please call your CENECO Call Center at telephone numbers 458-6777 local 1101, 1102, 1103 and 1107.