CENECO SETS POWER INTERRUPTION ON SEPTEMBER 27

Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on September 27, Sunday. This is to ensure reliability of distribution lines to avoid further serious damages that will result to major interruptions. Details of this outage are as follows:

Date: September 27, 2020 – Sunday


Reasons:

 

• Conversion of 25 spans, 1-phase to 3-phase primary lines and mid-span erection of additional one 35ft. pole (to correct long spanning) with its accessories;

• Replacement of eight 35ft. rotten poles with its accessories (to be converted into 3-phase); and

• Installation of three 100kVa distribution transformers (platform) with its primary metering at Prk. Pahu, Brgy. Dulao, Bago City

 

Time: 8am to 5pm

 

Areas Affected: SF2 portion from Highway going to Purok Proper of Brgy. Dulao, including Brgy. Hall, Elementary, High School, Purok Reola, Purok Pahu, Purok Macasa, Purok Pucatod and Purok Pag-asa

 

Electricity consumers are further advised that, in the event of any power interruption, electrical switch/es should be turned-off for safety reasons. When electricity supply resumes, please provide allowance of about 10-15 minutes before switching on all electrical appliances and facilities to avoid power surge. For inquiries, please call your CENECO Call Center at telephone numbers 458-6777 local 1101, 1102, 1103 and 1107.

 

Sorry for the inconvenience.

 

(SGD.) MARIA AGNES L. CLARO
OIC – Office of the General Manager