CENECO SETS POWER INTERRUPTIONS ON JULY 3 AND 4
CENECO SETS POWER INTERRUPTIONS ON JULY 3 AND 4

Central Negros Electric Cooperative, Inc. informs its consumers that maintenance activities will be conducted on July 17 & 18, Saturday and Sunday. This is to ensure stability of distribution lines to avoid further serious damages that will result to major interruptions. Details of these outages are as follow:

Date: July 17, 2021 – Saturday
Time: 6am to 4pm

Reasons:
• Degassify and Preventive Maintenance Servicing of 10MVA Power Transformer, repair hot spot and installation of two auto reclosers for reliability purposes at Mt. View Substation, Buri Road, Brgy. Mandalagan, Bacolod City;
• Replacement of rotten poles covering MF4 & MF5 feeders;
• Line clearing covering of MF4 & MF5 feeders.

Areas Affected: MT. VIEW SUBSTATION

MF4 Bata Subd. Including GoldCrest Subd., and Octagon Village (Talisay), whole of Mt. View Subd. Including Porferia Subd., Sta. Clara Phase I, Villa Valderrama Subd., Sto. Rosario, Lacson St. (from Lopue’s Mandalagan to Bangga Pepsi), Mandalagan Highway, Circumferential Road, Federal Johnson Iron Works to Marapara Heights Subd., Bacolod Golf & Country Club, Montebello Subd., The Ruins, Theresa Dev’t. Corp. Subd.
MF5 Robinson’s Commercial Complex.


Date: July 18, 2021 – Sunday
Time: 6am to 4pm

Reasons:
• Degassify and Preventive Maintenance Servicing of 30MVA Power Transformer and repair hot spot at Alijis Substation, Alijis Road, Brgy. Alijis, Bacolod City;
• Line clearing covering of AF1, AF2, AF3, AF4, AF5, AF6 and AF7 feeders; and,
• Replacement of rotten poles covering AF1 to AF7 feeders.

Areas Affected: ALIJIS SUBSTATION

AF1 Portion of Alijis Road (Alijis Substation to areas before Good Year), Bacolod Girl’s Home, Prk. Pag-asa, John B. Lacson College, Pauline Village, ECC Villas, Greenplains Subd., Akina village, South Residences, Araneta Highway (Monark Eqpt. down to Medalla Elem. Sch.), Bel-Air Subd., Woodstock Subd., Villa Cristina Subd., Prk. 8 Baybay, Gardenville Subd., Florenceville, ManVille Subd., Akina Village.

AF2 Portion of Alijis Road (Alijis Substation to areas before Maranatha Sch.), Baronessa Metal Corp., part of GreenplainsSubd., Araneta Street, Magsaysay Ave. to Sugarland Hotel, Luxur Place (former Bacolod Convention Plaza and Hotel), Teleperformance, Bacolod Police Station, Goldenfield Commercial Complex, Magsungay, Henrietta Village, Airport Subd., Calong-Calong, Villa Esperanza, Palmas Del Mar, Orient Marine, Villa Servando, Golden River Village.

AF3 Alijis Road (from Alijis Substation to Pagla-um Village), ProvindenciaSubd., Prk. Gaisano, Celita Village, Negros Metal Corp. – ACCO Housing, La Villa Guadalupe Phase 1&2, Cosmos Bottling, Hillside Subd., La Salle Ville, Mt. Carmen Ville, Hermelinda Homes,Kabugwason, East Homes 4,5 and 6, Lion Ville, Pedrosa Village, Bacolod Homes Royal, Camella South, St. Vincent’s Subd., Grandville 1,2&3Subd., Forest Hill, Had. Gonzaga,Brgy. Mansilingan, Green Acres Subd., Villa Magdalene, April Joseph mansilingan, Olympia Village, Lolita Heights, Regent Pearl-Alijis and Panaad Site, FelisaSubd.,Paglaum Village.

AF4 TRANSCOM, Back of Alijis Substation, Oriental & Motolite, A1 Gas, Viva, Alijis Road (from Alijis Substation to Airport Terminal), Bacolod Memorial Park, Asian Alcohol, Sasson Furniture, Jade Court II, VL Yap, Good Year and Teletech (Robinsons Metro), Lopue’s South Square
AF5 Baronnesa Metal Corporation

AF6 Mabini St. (from Libertad to San Sebastian St. including portion of Rosario St.), Bacolod City National High School, City Heights, BAC-UP 6, Espinos Village, Victorina Heights, Puentebella Subd., Rosario Heights, BM ACMA, Bakyas, JJ Gonzaga, Purity Home Owner’s Asso., CERES Motorpool, P & NB Subd., portion of Mansilingan, Brgy. Vista Alegre and BACIWA Vista Alegre Pumping Station, From Alijis Substation to May Quiachon, GarcesSubd., dead end of primary line at Taculing Elementary School, Prk. Kabulakan

AF7 New Coca – Cola Plant (Mansilingan)

Electricity consumers are further advised that, in the event of any power interruption, electrical switch/es should be turned-off for safety reasons. When electricity supply resumes, please provide allowance of about 10-15 minutes before switching on all electrical appliances and facilities to avoid power surge. For inquiries, please call your CENECO Call Center at telephone numbers 458-6777 local 1101, 1102, 1103 and 1107.